The project entailed the fabrication and erection of a curved plate fabricated main entrance arch with the suspended tubular round shaped Globe Bar. Steel was chosen because of the fact that complex shaped curve could not be achieved in concrete in the short space of time. Steelwork the obvious choice to give client the architectural shape. The Globe Bar, a steel structure was required to receive glass panels.

The casino arch structure was fabricated in the biggest possible elements, which left the least site welded connections for erection on site. Erection of the arch legs was done using a 220 ton crane on a suspended fully propped slab, while lifts were taking place. The main contractor and sub-contractor co-ordinated full system of back propping and stripping to accommodate client budgets. The main arch is a composite steel and concrete structure with re-bar fitted during the fabrication process. Once erected and site welded, concrete was pumped inside the plate arch using a specially designed concrete slurry.

The Globe Bar was fully constructed offsite to get the geometry 100% correct. The structure was then divided into segments and welded in the biggest transportable units. Segments were then bolted and site welded. A sacrificial inner structure of I-beams was constructed and the external frame of the Globe was pre-assembled on the inner frame to get geometry correct and to ensure the fit of glass panels. Mobile cranes and tower cranes were used during the erection of the Globe Bar suspended off the main arch legs. The last capping of the arch could only be installed once the Globe Bar was suspended from the arch legs.

Some challenges in implementing this project included keeping elements with transport sizes, within 220 ton crane lifting radius, design of backpropping to accommodate 220 ton crane on 3 levels of slabs, erection of the members within crane capacity and site splicing (bolting and welding at high levels).

PROJECT OVERVIEW
Tons of steel used ± 100 tons
Structural profiles used Plate, Tube, All Hot Rolled Members
Type of cladding Glass
Project Team Role Company
Client/ Developer Sun International
Architect LYT Architects
Structural Engineer WSP
Quantity Surveyor MLC
Main Contractor WBHO
Steelwork Contractor Cadcon
Structural Steel Detailer DN Design
Bekker Steel
Steel Erector On Par
Cladding Contractor Façade Solutions
Corrosion Protection
Paintwork Contractor
Dram