Project Type

Submitting Company (Non-SAISC Member)

STRUXIT

Location

Project Team Interview Case Study

Project Overview

Club Med’s Village at Tinley Manor, KwaZulu-Natal, is a landmark leisure development – described as the most significant hospitality project in South Africa since Sun City. The roof structures across the resort were designed to evoke natural forest canopies: low-profile, wide-spanning, and visually weightless. The defining feature is the main entrance canopy – an 11-metre column-free cantilever that frames the arrival experience for international guests, accommodates bus and shuttle turning radii, and eliminates the risk of vehicle collision with support columns. The roof system comprises conventional structural steel using Universal Beams, Cold-Formed Lipped Channels, Equal Leg Angles, Flat Plates, and curved CHS ‘tree columns’ that echo the forest concept. Four primary 27-metre roof trusses extend deep into the lobby to act as a tie-back counterweight system. A girder truss near the cantilever tip distributes loads across all four trusses, creating a unified rigid diaphragm. Diagonal bracing on both top and bottom chords substitutes for geometrically precluded knee bracing. Total steel tonnage: 70 352 kg. Steelwork contractor: Ogilvie Engineering. Steel detailer: PSM Pty Ltd.

Steel Profiles Used

  • Date of Steelwork Completion
    2025-09-01
  • Tonnage
    70
  • Hot Rolled Structural Sections
    Universal Beams, Equal Leg Angles
  • Plates
    Flat Plates
  • Cold Formed Structural Sections
    Cold-Formed Lipped Channels (CFLC)
  • Tubes and Pipes
    Circular Hollow Sections (CHS)

Project Details

Fabrication was executed by Ogilvie Engineering at their local KwaZulu-Natal facility. The most complex elements – the rolled and curved CHS tree columns – required trial rolling and test welding to assess visible deformation before full production commenced. Engineers and architects inspected the fabrication workshop during the process to establish acceptable weld and connection finish standards. The connection strategy was deliberately split: all shop welds were completed in controlled factory conditions, with hot-dip galvanizing applied prior to dispatch. Site welds were avoided entirely to preserve the integrity of the corrosion protection system. Bolted splice joints were used for transportation efficiency and to simplify on-site erection. Complex connections were modelled across three integrated platforms – Prokon Frame for structural analysis, Revit for general arrangement and detailing, and Tekla Structures for full 3D assembly review. This multi-platform BIM approach detected spatial clashes and constructability issues before a single piece of steel was cut, eliminating the need for site modifications and ensuring that the finished product matched design intent precisely.
The resort site was dense and constrained, with seven concurrent packages and seven contractors operating in close proximity. Restricted access roads and tight turning radii made traditional long-bed steel delivery impossible. No heavy cranes could be deployed; erection relied on mobile cranes, a spider crane for confined interior lifts, and bespoke manual lifting rigs where necessary. The steelwork contractor coordinated deliveries to strictly defined dates and areas, ensuring continuous erection flows without on-site material accumulation. Stakeholder meetings were held weekly – and sometimes daily – to manage sequencing across all packages. Pre-cambering of trusses was incorporated at fabrication stage to compensate for anticipated deflections under dead load, enabling accurate erection without site adjustment. No site welding was required. The pre-cut, pre-drilled, and pre-galvanized nature of all members reduced site waste, minimised chemical exposure, and shortened the programme on a congested coastal site.
The primary structural challenge was the 11-metre entrance canopy cantilever. A hipped roof profile with minimal structural depth – mandated by the architectural eaves requirement – severely restricted the available depth for the structural system, making it acutely susceptible to deflection. Traditional knee bracing was geometrically precluded. The soffit carried a heavy timber ceiling, adding significant dead load at the tip of the cantilever. Wind uplift over the full service life in the coastal KwaZulu-Natal environment added further complexity. The solution deployed four primary 27-metre roof trusses extending deep into the lobby, using the building’s own mass as a counterweight tie-back system. A girder truss near the cantilever tip acted as a load distribution mechanism, sharing forces evenly across all four primary trusses. Diagonal bracing along both top and bottom chords transformed the system into a space-frame-like diaphragm capable of resisting lateral forces without sacrificing the thin profile. An early spatial redesign also allowed two additional central columns to be introduced, reducing the cantilever from an initial 13 metres to 11 metres, significantly lowering induced forces.

Benefits of Steel in this Application

Steel was the only material capable of delivering this project’s architectural and functional intent. Concrete would have required structural depth that compromised the slender eaves profile and critical sightlines from 430 hotel rooms. Timber could not achieve the span-to-depth ratio needed for the floating canopy effect. Structural steel’s exceptional strength-to-weight ratio enabled 11-metre cantilevers, vast column-free spans, and hipped roof profiles that remain visually thin. Its formability allowed the fabrication of rolled and curved CHS tree columns – organic branching assemblies that reinforce the forest canopy concept architecturally. The lightweight superstructure simultaneously reduced foundation loads and overall material quantities. The full coating specification – hot-dip galvanizing with Zinc Phosphate Epoxy Primer (Plascoguard 75) and Plascothane 9000 Polyurethane topcoat – provides a 15-year maintenance cycle with cathodic protection redundancy. Steel is 100% recyclable at end of service life, and the zinc galvanizing process recovers and reuses the zinc coating, closing the material loop.

Testimonials

“What began as a daunting structural challenge evolved into one of the most rewarding aspects of the project. By trusting the process, leveraging the expertise of our mentors and collaborating as a team, we delivered an 11-metre cantilever steel roof that is both architecturally stunning and structurally audacious, yet entirely sound.” – Alexia, Engineer, STRUXIT

“It’s not just the engineering details that made it work – it’s the continuous engagement with different stakeholders that helped build the biggest leisure development in South Africa since Sun City. Club Med wasn’t just another project on my list, it was my opportunity to contribute to the ever-growing North Coast.” – Project Team Member, STRUXIT