Project Overview
Futurecon was awarded the contract for the supply and erection of the LSF for the internal and external walls and roofs, clad, lined and insulated with windows installed. From 27 July 2020 they had to complete the project in 10 weeks on 27 September 2020.
The project entailed the supply of 10 000m2 of hospital wards and associated buildings, housing beds in general wards, and in high and intensive care. The foundations were supplied by Concor.
Futurecon had to hand over 1 000m2 of hospital buildings per week. And they kept to the programme, barring two weeks when they were not allowed onto the site due to disturbance caused by the local communities. They used fibre cement external cladding, supplied by Etex Group (Marley Building Systems). OSB timber strips were used as thermal break between the external cladding and the LSF. A vapour permeable membrane was installed around the outside of the wall frames to waterproof and draughtproof the buildings, while allowing any vapour in