Project Type
Location
Steel Profiles Used
  • Date of Steelwork Completion
    2025-10-14
  • Tonnage
    103
Project Overview

Cellular beams were installed across the building span to support cast-in-place floors. The result is a rigid, grid-like framework that strengthens the entire structure.

Project Details
Fabrication was interesting. The challenge was installation. Holes through the wall were cored and usually misaligned.
Access to work area/ space was a challenge. Solution was to work over weekends and holiday while civil teams were away.
Testimonials

Providing a standard system with clear spans really future-proofs the building for future generations, even if internal partitions are removed or shuffled in future.

Annual Closure Notice

We will be closed from 12 December 2025 to 7 January 2026.

You are welcome to continue sending enquiries or membership applications, and you can still place orders online during this period. We will respond as soon as we return. Please note that any orders placed after 12 December 2025 will be fulfilled from 7 January 2026 onwards.