Project Type
Steel Profiles Used
  • Date of Steelwork Completion
    2020-09-30
  • Tonnage
    90
  • Hot Rolled Structural Sections
    Universal Beams (I Sections), Equal Angles
  • Plates
    Hot Rolled Sheets
  • Tubes and Pipes
    Structural Tubes & Hollow Sections – Rectangular, Structural Tubes & Hollow Sections – Round, Structural Tubes & Hollow Sections - Square
Metal Cladding and Roofing Overview
  • Cladding Profile
    Ziptek 420 - Concealed Fix (Global Roofing Solutions)
  • Cladding Tonnage
    18
Project Overview

The client's brief was replacement of the uncovered pool and stands with a covered arena while retaining the original 1927 northern entrance.

Roof split into repetitive RC eastern portal bay of 9.0m span by 8.0m height, and irregular long span portal steelwork roof over pools
Apex is sliding on plan by 20m over full length of roof (360mm step per m run) but at same height of 13.25m above ground level
Main span is 38m span between eastern RC portal and western RC column
RC cantilever of 5m, then 720x300x137kg/m plate girder steel rafter spanning 33m
Connection between RC and plate girder rafters are high moment connections using Peikko COPRA M39 Couplers – first of its kind in Africa – transferring up to 544kNm on the beam-to-rafter connection and 848kNm on the rafter-to-column connection
Stability of main roof provided by two CHS braced bays and RC portal beams in these bays for north-south direction, and by double portal frames in the east-west direction
Cold rolled lipped channel purlins take double curvature of roof surface to support Lambdaboard thermal & sound insulation and Zip-Tek 420 sheeting by GRS
Over 1927 heritage northern entrance, RHS columns are used to support last bay at façade line, plus UB cantilever purlins for entrance canopy
Façade support girts are SHS elements between columns

The new design encompassed 2,750m2 under roof, including changing facilities, a multi-purpose area and two state of the art pools for waterpolo and swimming.

Project Details
Plate Girders – PG720x300 (20mm Flange / 8mm Web), Purlins - CFLC225*75*20*3.5 (Min 200Mpa) , Cantilever Purlins – UB406x178x54, Rafter Cross Bracing & Tie beams - CHS127.0*3.0, Façade support rails – SHS120x120x4 / RHS200x150x6, Gable columns – RHS300x140x8, Sag Bars - L60*60*4 , Gutters – 3mm Mild Steel. Material specification and design requirements: Plate Girders – Sub Merged Arc welding 8 – 10m Partial Penetration CFW Purlins - CFLC225*75*20*3.5 (Min 200Mpa) Welding requirements - AWS D1.1 / Only Certified Welders UB406x178x54 cantilever beams site welded to cast in plates Corrosion protection Hidden steelwork & Plate girders – Sand blasted to SA2.5 /Type IA Architecturally exposed steelwork – Sand Blasted to SA3.0 / Type ED Purlins & Sags – CFLC Hot Dip Galvanized to Min 85 Microns Gutters – Hot Dip Galvanized All Bolts – Hot Dip Galvanized
Steelwork Erection Cranes utilized: - 25ton Mobile crane for offloading steelwork, stacking and infill work - 160ton Mobile crane to lift Fully assembled Plate girder portal frames - Assembled portal frame weight: 5.5 ton - Plate girder erection on 16th and 17th January 2020 - Bulk of remaining roof steelwork erected up to Covid lockdown in March 2020. - Last sections completed in May & June 2020 to main roof. Due to program constraints the swimming pool construction commenced at the same time as the steel fabrication and corrosion protection. Scaffold platforms were constructed inside the swimming pool below each portal frame assembly to support the steelwork ahead of being lifted. Each portal frame is unique and hence great care had to be taken to ensure each assembly have been assembled and placed accurately. Due to space constraints on site, the erection crane had to be set up in the road. Concrete columns had to be cast extremely accurate with Peikko COPRA Couplers in place. The Cladding Journey - Early-stage engagement with GRS Roofing to define sheeting constraints for double curvature. - Several workshops and proposal on tapered sheets, step requirements at critical junctions and purlin requirements - GRS Zip-Tek 420 sheet proposed from Chromadek Z200 sheet. - Detailed sheeting drawings and details done by GRS in agreement with Architect and Structural Engineer - Full scale worst bay mock-up done at GRS to confirm concealed fixing of Zip-Tek 420 sheet adequate to twist - Over purlin integrated Lambdaboard acoustic and thermal insulation panels proposed by Architect reviewed and approved by GRS Roofing - Insulation, sheeting and flashings installed by Lowveld Roofing Solutions
Design challenges - Creating a sleek slender structural solution within a long-span irregular architectural space = portalized plate girder solution to optimize structural depth High moment portal connections at end of plate girders to RC supports that are visible and needed robust yet elegant solution = Peikko cast-in COPRA coupler solution Corrosion protection within aquatic environment = specify aggressive coating system to plate girders and 85-micron min coating thickness to galvanized cold rolled sections Fabrication challenges - CFLC material had to be SAE1008 with min 200MPa material grade. Since SAE1008 CQ material do not come with a material certificate, material samples from two coils were sent to Metlab to be tested. QC passed coils were allocated, quarantined and used specifically for KES. The minimum galvanized coating thickness requirement for the CFLC material were 85 microns. Due to the influence the material composition of thin gauge material has on the galvanized coating thickness, the code minimum acceptable thickness is 70 microns. Similar samples to the above were hot dip galvanized prior to rolling and manufacturing of the purlins to ensure the engineer’s minimum thickness of 85 microns could be guaranteed. Detail modelling had to be done carefully due to the twist on purlins. High levels of quality control were required to ensure all steelwork have been fabricated accurately.
Benefits of Steel in this Application

High strength to weight ratio ideal for long span roofs
Off-site fabrication lends itself to the irregular components of the feature roof – itemized component design and fabrication
Compatibility with regular support RC frame
Speed of erection
Competitive market locally
Local skill set of subcontractors
Aesthetic simplicity